United States Steel Adjusts Hot Strip Mill Operating Configuration to Support Asset Revitalization Process

12.13.2016

PITTSBURGH, Dec. 13, 2016 /PRNewswire/ -- United States Steel Corporation (NYSE: X) announced today it will adjust its hot strip mill operating configuration to support a previously announced asset revitalization process.  The company will begin processing slabs on the currently idled hot strip mill at Granite City Works in Granite City, Ill., in mid-February 2017.  U. S. Steel intends to source slabs from its own domestic facilities. 

U. S. Steel is making this adjustment to its hot strip mill operating configuration to provide better alignment with customer needs and improve service while increasing the pace of its asset revitalization plan.  The company plans to take periodic outages at Gary Works (Gary, Ind.), Great Lakes Works (Detroit, Mich.), and Mon Valley Works (Pittsburgh, Pa.) to improve the capabilities and reliability of the hot strip mills. 

The Granite City Works blast furnaces and steelmaking facilities were idled in December 2015 and the hot strip mill was idled in January 2016 in response to challenging global market conditions.  The blast furnaces and steelmaking facilities will remain idled.  The pickle line, cold mill and finishing lines at Granite City Works will continue to operate

United States Steel Corporation, headquartered in Pittsburgh, Pa., is a leading integrated steel producer and Fortune 250 company with major operations in the United States and Central Europe.  For more information about U. S. Steel, please visit www.ussteel.com.

 

SOURCE United States Steel Corporation

For further information: Erin Dipietro, Manager, External Communications, (412) 433-6845, emdipietro@uss.com